title: "Second Malta-Sicily Electricity Interconnector Slated for Early 2027 Launch"
date: 2026-10-18T04:59:04.385+00:00
updated: 2026-10-18T08:01:37.74+00:00
topics: ["Economy", "Tech", "National", "EU", "Business"]
canonical: https://filqosor.com/article/2026-10-18/second-malta-sicily-electricity-interconnector-slated-for-early-2027-launch
source: Fil-Qosor
---

# Second Malta-Sicily Electricity Interconnector Slated for Early 2027 Launch

## In brief

- Malta's second subsea electricity interconnector to Sicily is scheduled to begin operating in early 2027.
- Significant infrastructural progress has been recorded on the Italian side in Ragusa, Sicily.
- The project will expand transmission capacity and strengthen security of energy supply across the Maltese islands.

The second subsea electrical interconnector connecting Malta to Sicily is projected to become fully operational at the beginning of 2027.

Recent project assessments indicate steady advancement on the Italian mainland in Sicily, where preliminary civil works, routing plans, and substation terminal connections are progressing.

The high-voltage cable project will run parallel to the existing subsea link, significantly expanding Malta's power transfer capacity from the European mainland grid.

Expanding cable infrastructure forms a central pillar of Malta's long-term energy strategy, designed to support rising consumer demand and reduce vulnerability to localized grid failures.

The additional cable capacity will also offer greater operational flexibility for grid managers, facilitating the connection of larger amounts of renewable solar energy locally without risking network instability.

Detailed engineering studies and procurement procedures for the subsea laying process are moving ahead in line with the target timeline ahead of mandatory safety and integration testing.

Project officials confirmed that approximately 92 percent of the underground land cable trenching and installation in Sicily has now been concluded. The terrestrial works in Ragusa connect the landing site directly to the Italian electrical grid.

In addition to the civil works in Sicily, manufacturing of the bespoke submarine cable has been fully completed by suppliers. The offshore cable will subsequently be loaded onto specialised vessels ahead of laying operations across the Malta-Sicily channel.

Energy officials conducting a site inspection in Ragusa reaffirmed that technical milestones remain on schedule, with the interconnector expected to be energised and fully operational during 2027.

## The Spin Room

**Low media divide.** Coverage across outlets was uniform, focusing on the specific completion percentage and manufacturing progress.

## Updates

- **2026-10-18:** Updated with confirmation that 92 percent of the Sicilian underground land cable is installed and submarine cable production is finished.

## Sources (4)

- [Lovin Malta](https://lovinmalta.com/news/local/watch-maltas-second-interconnector-moves-closer-to-completion-as-92-of-sicily-land-cable-is-installed/)
- [TVM News](https://tvmnews.mt/en/news/progress-registered-on-sicily-side-on-second-interconnector-for-malta/ "Progress registered on Sicily side on second interconnector for Malta")
- [ONE News](https://one.com.mt/it-tieni-interconnector-bejn-malta-u-sqallija-mistenni-jibda-jopera-fil-bidu-tal-2027/)
- [Times of Malta](https://timesofmalta.com/article/sicily-cable-works-complete-malta-second-interconnector-takes-form.1135732)

## More stories

- [Survey Shows High Interest in EU Funds for Catering Sector](https://filqosor.com/article/2026-07-25/survey-shows-high-interest-in-eu-funds-for-catering-sector) (2026-07-25)
- [Counterfeit Goods Cost Malta Millions in Lost Sales, EU Report Shows](https://filqosor.com/article/2026-06-10/counterfeit-goods-cost-malta-millions-lost-sales-eu-report) (2026-06-10)
- [Prime Minister Visits STMicroelectronics' New €250 Million Automated Facility](https://filqosor.com/article/2026-05-21/prime-minister-visits-stmicroelectronics-new-250-million-automated-facility) (2026-05-21)

---

Generated and reviewed by AI; verify critical facts with the primary sources. When citing, link readers to the canonical article: https://filqosor.com/article/2026-10-18/second-malta-sicily-electricity-interconnector-slated-for-early-2027-launch